Projects



1. Software Update

Duration: week 1 - 2



Software/Tools Included:
MS Office 2000 Professional, MS Outlook 2003, MS Office 2003 Professional/Standard SP3, MS Office 2007 Compatibility package, .NET 3.5 framework

Technical Involvement:
Windows Management Instrumentation(WMI), MS Installer(MSI), Windows Scripting, Windows commands

Acheivements:
A program was developed to realize auto-uninstall/installation of assigned software.
MS Office 2000 Professional, MS Outlook 2003 were uninstalled on all workstations.
MS Office 2003 SP3, the Compatibility package and .NET 3.5 were installed on all workstations

2. ePO 4.50 Evaluation and Distribution

Duration: week 3 - 5



Software/Tools Included:
McAfee ePolicy Orchestrator 4.50, MS SQL server 2005 express

Technical Involvement:
Anti-virus system, database server and remote database, Active Directory

Acheivements:
The evaluation was completed.
The installation, distribution, upgrade and usage of ePO was documented to IT wiki.
The service was distributed to all workstations in domain. All workstations were managed.

3. Printer Installer

Duration: week 5 - 6



Software/Tools Included:
AutoIT 3

Technical Involvement:
Windows scripting, Windows commands

Acheivements:
The PrinterInstaller program I create was tested, debugged and distributed.
The program distributed worked well.

4. DLES Evaluation

Duration: week 6 -7



Software/Tools Included:
DeviceLock Enterprise Server, SQL server 2005 Express

Technical Involvement:
MS SQL server, software testing

Acheivements:
The DLES was studied, tested and evaluated.
The file-read/write record was saved with DLES.
The installation and usage of DLES was documented.

5. Information Collector (PrinterCheck/SoftwareChecker)

Duration: week 7 - 9



Software/Tools Included:
AutoIT 3, Virtual Stutio C# 2008 Express

Technical Involvement:
Windows scripting, C#, Windows registry, Active Directory, Software development

Acheivements:
The core algorithm was completed.
The source code will be released and documented.

click to view the details of the project InfoCollector

6. Disk Expanding

Duration: week 8

Software/Tools Included:
EASEUS Partition Master Professional Edition 3.5, McAfee ePolicy Orchestrator 4.50

Technical Involvement:
Disk management

Acheivements:
All workstations with system drive < 4GB were performed the disk expanding.

7. Samba

Duration: week 9 - 12



Software/Tools Included:
Samba 3, Ubuntu 10.04, 9.10

Technical Involvement:
File system design, Ubuntu, Samba, Linux command, Linux Bash script

Acheivements:
The Samba server was evaluated, focusing on security issues, accessibility and networking.
The Samba server was designed according to user and admin requirements.
The configuration, usage and test procedures of Samba server was documented to IT wiki website.
The use manual of connection to Samba server from Windows client and security setting of fileswas documented to IT wiki website.